September 13, 2002
The Honorable Richard Meserve Chairman Nuclear Regulatory CommissionOne
11555 Rockville Pike Dear Chairman Meserve, We are writing with regard
to the request by Nordion, Inc. to amend an existing export license (XSNM
03060/02, Federal Register, We strongly oppose this
request for two reasons: First, it is contrary to the requirements of the
Schumer Amendment (Section 134 of the Atomic Energy Act of 1954, as amended, 42
U.S.C. 2160(d)), and the Commission's implementing regulations (10 C.F.R.
110.42(a)(9)). Second, it is inimical
to the common defense and security, and thus prohibited under Section 53 of
the Atomic Energy Act of 1954, as amended (42 U.S.C. 2073, and 110 C.F.R.
110.42(a)(8) and 110.45(a)). To be
specific: 1. The Schumer amendment
prohibits the export of HEU which can be used directly to make nuclear
weapons unless, inter alia, the
applicant is actively pursuing conversion to low enriched
uranium (LEU), which is unsuitable for weapons.
The goal of the law is to reduce risks of nuclear terrorism and nuclear
proliferation by phasing out commerce in HEU as quickly as possible, while
avoiding the interruption of legitimate nuclear activities as long as foreign
operators comply with the laws provisions.
Approval of the applicants proposed license amendment would violate
this law by authorizing the export of HEU beyond the date when the applicant
can reasonably be expected to convert to LEU, thereby permitting the applicant
to continue exporting HEU from the 2. The longstanding policy
of the Background
Decades ago, before the
terrorism and proliferation risks of HEU were fully appreciated,
the As the new MAPLE facilities
were under construction, in late 1998, Nordion requested a license to export
130 kg of HEU in targets for the MAPLE reactors (XSNM 03060, the license that
the applicant now seeks to amend for the second time). The Nuclear Control Institute (NCI)
petitioned the Commission for leave to intervene and requested a hearing on
grounds that the Canadians still lacked an active program to convert to LEU
targets.[5] The NRC responded by calling a public meeting
in June 1999 at which both the Institute and the applicant testified, and the
Commission later confirmed NCIs concerns, stating: At the time NCI filed its
pleadings with the Commission [December 1998], the continuing existence and
extent of an active program to develop LEU targets for use in the MAPLE
reactors were not readily apparent.[6] Nordion again pledged to convert to LEU as
quickly as possible, which it said would require three to five years
indicating that conversion to LEU would be completed by 2002 to 2004.[7] On the basis of this commitment, in June
1999, the Commission conditionally approved the license, imposing annual limits
on the HEU exports and requiring the applicant to submit an annual report on
its progress towards conversion. The NRC
also warned explicitly that if it later determined the applicant was in
violation of the Schumer amendment, the Commission may modify, suspend, or
revoke the license.[8] Following submission of
Nordions first annual report, NCI requested another public meeting, which the
Commission convened in July 2000.
Despite the passage of another year, the applicant had made no
substantial effort toward conversion and now claimed it would require another
five years indicating that conversion to LEU would be completed by 2005.[9] The applicant also indicated that the
anticipated start-up of the MAPLE facilities had been delayed. In our testimony, NCI argued
that there was no reason that Nordions delay in start-up of the MAPLE
facilities should delay its conversion to LEU targets. Assuming the applicant were pursuing
conversion in good faith, we argued, the delay should mean it would require one
year less of HEU supply. We concluded:
To avoid export of any HEU surplus to the applicants needs, in accordance
with During the first half
of 2001, technical problems further delayed the start-up of commercial isotope
production at the MAPLE facilities until at least 2003, but Nordion nonetheless
continued to export MAPLE HEU targets.
In response, in July 2001, NCI urged the Commission to declare a
moratorium on further exports of HEU targets for the MAPLE reactors after the
end of 2001 by which time Nordion already will have acquired its desired
working inventory of 40 kg of such targets until the start of commercial
isotope production using these targets.
We added: Given that Nordion will not start commercial isotope
production until 2003, there is no justification for Nordion to import any
further HEU targets from the In its May 2001 annual
report to the Commission, Nordion also delayed again its planned conversion to
LEU targets, claiming that it still needed another five years thereby
indicating the completion of conversion to LEU by the end of 2006. The Institute took strong issue with this
claim in its July 2001 response to the Commission, explaining: There is no reason that the continued delay in start-up of commercial operation at the MAPLE facilities using HEU targets should delay significantly, if at all, Nordions conversion of such production to LEU targets. In other words, the longer the delay persists, the smaller the amount of HEU MAPLE targets that Nordion should require prior to converting to LEU targets. Accordingly, the Commission should reduce the total amount of HEU MAPLE targets that Nordion can export under XSNM 03060 approximately in proportion to the delay in the start-up of commercial operation at the MAPLE facilities. One straightforward way for the Commission to accomplish this would be to enforce strictly the terms of the license, as it has done so far, by insisting that any HEU licensed for export in a given calendar year but not exported during that year may not be exported subsequently. By hewing to this principle, the Commission could reduce the total amount of HEU MAPLE targets licensed for export simply by insisting that the current moratorium on such exports be extended through the end of 2002. Doing so would ensure that the applicant has continued incentive to maintain its planned schedule for conversion to LEU targets. It is imperative that the applicant not be permitted to use the delay in start-up of commercial operations at the MAPLE facilities as an excuse for further delays in its conversion of production to LEU targets.[14] Nordions Proposed License Amendment Nordions latest
request attempts to do precisely what we warned the Commission about last year
that is, to use the delay in start-up of the MAPLE facilities as an excuse to
delay still further the conversion to LEU targets. If the Commission were to acquiesce in this
demand, it would reward the applicant for its past foot-dragging on conversion,
eliminate any incentive for the applicant to pursue conversion expeditiously,
signal that the United States is not serious about enforcing the Schumer
amendment and permit the applicant to increase its already substantial
stockpile of HEU all in direct contravention of U.S. law and policy intended
to ensure the common defense and security. Nordions request
proposes three changes to its existing license: (1) an extension of the
expiration date from July 31, 2004 to December 31, 2007; (2) an increase in the
amount of HEU authorized for export from 90.4 kg to 130.6 kg; and (3) the
elimination of annual sub-caps on HEU exports, instead requiring the applicant
only to inform the Commission two months prior to each shipment. Nordion attempts to justify
this amendment request in its annual report to the Commission of First, Nordion once again
has delayed its schedule for conversion to LEU targets. Despite supposedly pursuing conversion in
good faith during the past three years, Nordion still claims it will require
another five years indicating that 2007 is the earliest time that the MAPLE
reactors and the NPF could convert from HEU to LEU targets.[15] Strangely, Nordion reports that despite
delays during Phase 2 of its conversion program, the applicant nevertheless
will meet its deadline for completion of Phase 2. The only possible explanation is that Nordion
padded its original conversion schedule for Phase 2, which confirms our prior
warnings to the Commission. Moreover,
without explanation, Nordion now has added another year to Phase 3 of its
conversion schedule, increasing it from three to four years. The report claims that, In previous Annual
Reports, MDS Nordion has provided a comprehensive explanation of the reason for
its estimate that . . . at least four years will be required for Phase 3.[16] In reality, Nordions previous reports and
testimony have claimed Phase 3 would require at most three years, and the
applicant never has provided a satisfactory explanation of why this final phase
of conversion would require even that long, let alone four years. Indeed, Nordions actions
during the last year suggest that it continues to drag its feet on conversion
to LEU targets. For example, while the applicant has irradiated prototype HEU
MAPLE targets in the NRU reactor to expedite the future start-up of commercial
isotope production in the MAPLE facilities using HEU targets, it has refused to
similarly irradiate prototype LEU MAPLE targets in the NRU to gain information
that could expedite future conversion of the MAPLE facilities for LEU targets. Likewise, while the applicant reportedly has
tested the NPF prior to commercial start-up by processing unirradiated HEU
MAPLE targets, it has refused to do so with unirradiated LEU MAPLE targets,
which would facilitate future conversion by resolving outstanding technical
issues cheaply and quickly before the facility becomes contaminated following
processing of its first irradiated targets.
Indeed, the applicant has not even ordered the production of any LEU
MAPLE targets from BWX, its Second, the facts provided
by Nordion in the report and elsewhere indicate that the applicant, if it
pursues conversion to LEU in good faith, will need less HEU than the
Commission already has licensed for export, thereby undermining any
justification for the applicants proposed increase in the authorized
level of such exports. The annual report
projects that the MAPLE reactors will be brought into commercial operation no
sooner than the first half of 2003, which assumes that additional technical
problems do not arise.[17] Even if this optimistic forecast were
realized, the actual commercial production of medical isotopes at the MAPLE
reactors and NPF could not begin until 2004.
This is because, as we have explained previously, commercial production
cannot begin until the applicant has processed test elements in the facilities
and then obtained regulatory approval of the resulting medical isotopes from
Health Canada and the U.S. Food and Drug Administration, which the applicant
has testified requires six to nine months. Providing further evidence
that commercial production at the MAPLE facilities will not begin until 2004,
Nordion concurrently has requested a third amendment of another license (XSNM
03171/03) to export an additional 15 kg of HEU for production of medical
isotopes at the NRU facilities. The
first amendment to that license authorized 10 kg of HEU exports for production
at the NRU through at least October-November 2002. The second amendment to that license
authorized 10 kg of HEU exports for production at the NRU through
approximately the early summer of 2003.[18] This data indicates that isotope production
at the NRU requires approximately 5 kg of HEU every four months. Thus, the proposed third amendment, for an
additional 15 kg of HEU, indicates that Nordion foresees isotope production at
the NRU, rather than at the MAPLE facilities, through the summer of 2004. If the applicant avoids any
further delays and manages to commence commercial production at the MAPLE
facilities in mid-2004, and also meets its current schedule for conversion to
LEU targets by 2007, it would require only three years supply of HEU
targets. Based on the information
originally provided by the applicant, production at the MAPLE facilities will
require approximately 20 kg of HEU annually, so Nordion would have a total
requirement of about 60 kg of HEU in MAPLE targets prior to converting to LEU
targets. As noted, however, Nordions
current export license (XSNM 03060) already authorizes the export of 90.4 kg of
HEU for MAPLE targets. Thus, the
applicant has provided absolutely no justification for requesting an increase
in its authorized level of HEU exports for the MAPLE facilities. Moreover, Nordion already
has exported to Both Nordions proposed
amendment and its annual report suggest that the applicants main goal is to
ensure that it can quickly obtain a large supply of HEU from the United States,
in order to avoid future scrutiny by the Commission and future compliance with
U.S. statutory requirements.
Accordingly, the most likely explanation for the applicants request to
renew exports of HEU MAPLE targets prior to reducing its existing stockpile is
that it fears being cut off in the future for failure to comply with the
Schumer amendment. Similarly, the
applicants proposed amendment to eliminate annual limitations on HEU exports
suggests that it is trying to acquire as much HEU as quickly as possible, in
order to avoid future Additionally, we would like
to address several erroneous or questionable claims in the applicants
presentations to the Commission. First,
the applicant claims in its annual report that the adequacy of its physical
security measures should not be subject to further U.S. scrutiny because no
material has yet been reported stolen and because the Pentagon determined
several years ago that there was not a
genuine terrorist threat to these shipments or Nordions facilities.[20] Surely, the tragic
events of September 11, 2001,
and subsequent intelligence
reports, call into question such assurances. Foreign leaders and groups including Saddam
Hussein and al-Qaeda have tried repeatedly to obtain fissile material for a
nuclear weapon. Moreover, if a rogue
leader, terrorist organization, or criminal enterprise were to attempt to
obtain such material, it is quite possible they would view an obscure, lightly
guarded Canadian civilian facility or transport as one of the most propitious
targets. In this light, it is essential
that the Commission and the U.S. Executive Branch reexamine the adequacy of
Nordions physical security during transport and storage prior to considering
approval of any further HEU exports to the applicant. In addition, NCI believes that in the post-September
11 era, the Second, Nordion falsely
implies that an official of the U.S. Reduced Enrichment for Research and Test
Reactors (RERTR) program at the U.S. Argonne National Laboratory wrote in a
recent report that the applicant was making excellent progress towards
conversion to LEU targets.[21] In reality, this quote was used in Armando
Travellis public presentation to describe the work on isotope production by
his own program, which indeed has made great progress towards conversion to LEU
targets in countries such as Third, Nordion erroneously
implies that the Finally, Nordion has the
audacity to imply that its continued reliance on HEU targets, and failure to
convert to LEU, actually reduces rather than increases risks of nuclear
terrorism and nuclear proliferation because, as the targets are irradiated in
the MAPLE reactors, the total world supply of HEU will be reduced.[24] If one were to accept this specious logic, it
would mean the entire 25-year international nonproliferation and anti-terrorism
effort to convert reactor fuel and targets from HEU to LEU, spearheaded by the Summary and Recommendations Nordion persistently
has violated the requirements of the Schumer amendment by dragging its feet on
conversion to LEU targets. For example,
in 1999, it stated that such conversion would require another three to five
years. In 2000, it again stated that
conversion would require another five years.
In 2001, it once more stated that conversion would require another five
years. And in 2002, for the fourth
straight year, it again stated that conversion would require another five
years. Apparently, the applicant
believes that merely by repeating that conversion is only five years away, it
can satisfy the Commission that it is complying with the Schumer
amendment. Nordion already has
the two-year stockpile of HEU MAPLE targets that it previously reported was
sufficient for its commercial purposes.
Thus, there is no justification for any further exports of such targets
until at least the start of commercial production of medical isotopes at the
MAPLE facilities. Accordingly, the
Commission should insist that Nordion maintain its moratorium on exports of HEU
MAPLE targets until the start of such production, which cannot occur until at
least 2004. When and if Nordion begins
commercial production at the MAPLE facilities, the Commission could permit
resumption of exports under the existing license (XSNM 03060), if the license
still is valid and if the Commission deems the applicant still to be in
compliance with the Schumer amendment and other statutory requirements. However, if the license already has expired
by that time, Nordion should be required to apply for a new license rather than
merely an amendment to the earlier license, in order to afford the Commission
and the public the opportunity for a full review of the applicants compliance
with the Schumer amendment.[25] Admittedly, such an approach
could raise uncertainties for the applicant as to whether it will receive
future exports of HEU targets from the Lastly, we would
remind the Commission that this case has larger implications than just HEU
commerce in Thank you for your
consideration of this important matter.
We stand ready to meet with you and to provide further information upon
your request.
Alan J. Kuperman Edwin Lyman Senior Policy
Analyst President cc: NRC Commissioners Senator Charles E. Schumer[1] See, letter from Mathew George, Transnuclear,
Inc., to Edward Baker, Office of International Programs, NRC, [2] Fact Sheet: Nonproliferation And Export
Control Policy, Office of the Press Secretary, The White House, [3] Project Vinca Fact Sheet, [4] J.B. Slater, General Manager, Major Facilities Business Centre
Operations, AECL Research, The Program on Future HEU Supply for AECLs
Radioisotope Production Operation, [5] Petition of the Nuclear Control Institute for
Leave to Intervene and Request for Hearing, [6] [7] Transcript, Briefing on Proposed Export of High
Enriched Uranium to [8] [9] Transcript, Briefing on Proposed Export of High
Enriched Uranium to [10] Paul L. Leventhal and Alan J. Kuperman, Prepared Statement, Briefing on Proposed Export of High Enriched Uranium to Canada, U.S. Nuclear Regulatory Commission, public meeting, July 10, 2000, p. 10. [11] Staff Requirements Memorandum from Annette L.
Vietti-Cook, Secretary, to Janice Dunn Lee, Director, Office of International
Programs, [12] Letter from Alan J. Kuperman and Paul L. Leventhal, Nuclear Control Institute, to Chairman Richard Meserve, U.S. Nuclear Regulatory Commission, July 19, 2001. [13] Jean-Pierre Labrie, AECL, letter to Ronald D. Hauber, NRC, [14] Letter from Alan J. Kuperman and Paul L. Leventhal, Nuclear Control Institute, to Chairman Richard Meserve, U.S. Nuclear Regulatory Commission, April 4, 2002. [15] G.R. Malkoske, Vice-President, Nordion, Yearly Status Report for the U.S. NRC on the Progress of the Program and Canadian Cooperation in Developing LEU Targets for the MAPLE Reactors and the New Processing Facility, May 31, 2002, pp. 5, 21. [16] Malkoske, Yearly Status Report, [17] Malkoske, Yearly Status Report, [18] Malkoske, Yearly Status Report, [19] Malkoske, Yearly Status Report, May 31, 2002, pp. 6, 26; Grant R. Malkoshe, Application for the NRCs Withholding, from Public Disclosure, of the Confidential Annex to MDS Nordions Annual Report, Transmitted to the NRC on May 31, 2002, Pursuant to Condition No. 10 of License Number XSNM 03060, Affidavit of Grant R. Malkoske, p. 2. [20] Malkoske, Yearly Status Report, [21] Malkoske, Yearly Status Report, [22] Armando Travelli, Progress of the RERTR Program in 2001, paper
presented at the International Conference on Research Reactor Fuel Management
(RRFM 2002), [23] Malkoske, Yearly Status Report, [24] Malkoske, Yearly Status Report, [25] An adequate review is not possible if Nordions requests for additional HEU exports are treated merely as amendments to existing licenses, as with XSNM 03060/02, rather than as entirely new license applications. |